Thursday, August 30, 2012

Progress on the wood floor

The wood floor guys have made great progress today, and may finish today. The insulation crew finished their job today, which will keep the hot air outside.


The completed floor in the guest bedroom


Working on the master bedroom


Tile completed in the basement


The top view of the deck


Working on the hallway floor


Working on the great room floor

Wednesday, August 29, 2012

We have a cool house!

The air conditioning is up and working (in fact its downright chilly in the basement). Arctic Insulation was blowing insulation into the attic and over the garage so the cool will stay inside. The wood floor guys have finished Rita's sewing room, and are working in the guest bedroom. The guys also finished the basic construction of the deck.



The finished floor in the sewing room


Paper and wood in the guest bedroom


Arctic Insulation blowing insulation in the attic and garage


The basic structure of the deck is finished

Tuesday, August 28, 2012

We have AC!!

The geothermal guys completed the installation of the piping connected to the ground loops and the heating/cooling system. The materials for the deck were delivered today.


The pipes connecting the ground loops to the heat pump


The geothermal guys completing the installation


The deck materials delivered

Monday, August 27, 2012

Tile and flooring progress

As of today we have electricity in the house. Alliant finally installed the new meter one that will work with our solar system. The meter will run backward when we are producing more electricity than we use. The floor tile crew worked Saturday and Sunday to complete about 90% of the tiling job. The hardwood flooring was delivered today, with installation later this week.


The stacks of hardwood awaiting installation



The floor in the entryway


The floor in the laundry room


The floor in the master bath


The basement floor nearing completion

Tuesday, August 21, 2012

Painting and stone completed

The painters finished painting the ceiling, and painted the garage so our garage door can be installed. The stonemasons completed the stone on the west wall. When the gutters are installed, and the new exterior doors to replace the temporary ones now in place, the exterior of our new house will be finished.


Gravel to be spread under the new deck


Stonemasons beginning work on the front porch area



Painting completed in the garage


Ceiling painting completed (the walls will receive a second coat after the crown mouldings are installed)


The completed stonework on the west side

Friday, August 17, 2012

Ready for interior paint

Yesterday the painters finished the orangepeel finish on the ceilings and walls. Next week should see the completion of the interior paint and the deck. The retaining walls will be constructed soon.




Siding completed-west side




Porch area ready for stone


Siding finished-north side


Orangepeel-great room



Orangepeel-basement

Friday, August 10, 2012

Sheetrock completed, progress on siding

Today the sheetrock crew finished their job by taping and mudding the walls and ceilings in the house and garage. A final sanding and the walls will be ready for paint. The siding crew finished the north wall of the garage, and most of the east end of the house.


The finished west side (bare space wii be filled with stone)


Completed north end of the garage


The finished walls of the garage


The finished basement walls

Thursday, August 9, 2012

More sheetrock and siding

The sheetrock crew finished the rest of the installation, while the siding crew completed the south side and began the front side.


Installing siding on the front side


Completed siding on the south side


Completed sheetrock in the garage


Completed sheetrock in the great room


View from kitchen to master closet


The master bedroom




View from the master bath into the master closet


The basement man cave facing southeast


Man cave facing west

Basement bedroom

Wednesday, August 8, 2012

Sheetrock and siding

The siding and sheetrock crews made considerable progress today inside and outside of the house.


Sheetrock on ceiling - main floor


Sheetrock on the walls in the master bedroom


Sheetrock on the ceiling of the basement


Preparing to side the upper part of the south side


Siding on the lower part of the south side


The ledger plate for the deck on the north side

Tuesday, August 7, 2012

Progress update

Rita and I have been on vacation in Missouri with Matthew, Melissa, and our two oldest grandsons for the past week, so I will update progress on our house. While we were gone the electrical and plumbing systems were completed, and the the PV (solar) system was completed. As soon as we get our internet connection is made we can start producing electricity. The wall cavities between the studs were sprayed with one inch of closed cell foam. Today, Arctic Insulation placed fiberglass batts between the studs and covered it with a thick plastic vapor barrier. The sheetrock crew delivered a large amount today, and the sheetrock will be installed tomorrow. Friday, the siding that was delivered Monday will be installed.


The third post on the front porch


The insulation batts in place
 

Completed vapor barrier and sheetrock - basement



Great room - sheetrock and boxes of mud